When an FCC Order and the milestone rule disagree, which date is right?
Some FCC Orders state a milestone deadline that differs from the one 47 CFR 25.164 produces. We read every case and found most were not a legal question at all.
Published 24 November 2026
The question
The FCC's milestone rule, 47 CFR 25.164, counts each deadline from the grant of the licence (see our guide to FCC milestones). But the Order granting a licence sometimes states its own deadline, and on some licences the Order's date and the rule's date are months or years apart.
Section 25.164 allows for that: it applies "unless a different schedule is established by this chapter or the Commission". So when the two disagree, which date should a lawyer diary? We read every such case in our corpus, clause by clause, to find out.
What we found
Most of the disagreements were not about a different schedule. They were about a different start date.
The FCC's filing system records a "date granted" for each file. On the records in question, that field held the most recent action on the file, not the grant the Commission counted the milestones from. A licence granted years earlier and modified recently looked, on the public record, as if it had just been granted. Apply the rule to that date and every milestone comes out late.
How we could tell
Surety bonds. Under 47 CFR 25.165, a licensee must post its bond within 30 days of the grant (see our guide to surety bonds). The bond deadline is therefore counted from the same grant as the milestones.
As measured on 17 September 2026, nine bond deadlines in our corpus fell before the recorded grant date of their own licence, one of them by 2,383 days. A bond cannot be due before the grant it is counted from, so on those licences the recorded date could not be the grant. The Order's stated milestone was not a different schedule; it was the same rule applied to the right start date.
The rule we now apply
We publish the date an Order states only where a second date in the same document agrees with it:
- Take the bond deadline the Order states, and subtract 30 days (or one year and 30 days, for a streamlined small-satellite licence). That gives a grant date.
- Add the milestone's own interval from 25.164 to that grant date.
- If the result is exactly the deadline the Order states, the Order's date is published, labelled as the Order's, with the reconciliation shown.
There is no tolerance to tune: both directions use the same date arithmetic
that computes every other deadline we publish. Where the check passes, the
record says order_stated. Where it does not, the rule's date stands and the
disagreement stays visible as a finding.
What is still open
A handful of disagreements do not reconcile, for different reasons: an Order that records a bond as already posted rather than setting a deadline, so there is no second date to check; deadlines that belong to a later tranche of satellites added by modification; and one bond that sits further from the implied grant than the rule allows, which means one of its two dates is misread. Those stay open and visible, with both dates shown, rather than resolved by guessing.
Why it matters
A deadline computed from the wrong start date is wrong by the same amount on every milestone in the licence. Checking it against a second, independent date in the same Order is the difference between a calendar that looks right and one that can be shown to be right.
This note describes how Orbital Docket computes and checks deadlines. It is regulatory research that shows its working, not legal advice.