Tool
Satellite licence deadline calculator
Enter a date. Get the date the rule gives, with the paragraph it comes from and the version of the rule that was in force.
Three clocks: FCC milestones and the surety bond, the FCC petition window, and the ITU's limit for bringing a network into use. Not legal advice.
This page does one thing: date arithmetic under a stated rule. It holds no licence, no company and no filing, and it sends nothing anywhere. Once it has loaded it works with the network off. The same input gives the same date every time, because no model and no judgement is involved: an interval is added to a date.
FCC milestones and the surety bond
From the date a space station licence was granted: 47 CFR 25.164 and 25.165(a).
FCC petition window
From the date of the public notice that accepts an application for filing: 47 CFR 25.154(a)(2), then 1.4(j) when the last day is a weekend or a federal holiday.
ITU: bringing a network into use
From the date the Radiocommunication Bureau received the filing: No. 11.44 of the Radio Regulations.
What each answer is, and is not
It is the rule's date. The Order that grants a licence may state another, and the Commission may extend a date or waive a rule. Where an Order states its own date, that date governs, and it is what a subscription shows: the Order's words, the status, and whose licence it is. What Orbital Docket tracks.
It does not know your licence. Whether a rule applies at all is a question about the authorization: 25.164 excludes satellite digital audio radio and replacement space stations, a modification restates an earlier clock, and a licence granted in stages takes the earliest schedule. The calculator asks for none of that and so cannot answer it.
A date it cannot support is refused. A grant earlier than the first version of a rule held here gets no date for that rule. The federal holidays are generated from the same table the product's pipeline uses, for to . A window that closes after that is shown without the weekend-and-holiday step. A day the Commission's headquarters closed for weather, by executive order or in a government shutdown is also a holiday under 1.4(e)(1), and none is in the table.
This is regulatory research that shows its working. It is not legal advice.
The intervals this page applies
Generated from the product's rule files on every build, not typed into the page. Each row is the version in force now; an earlier date is counted under the version in force on that date, and the answer names it.
| Clock | Rule | Interval | Version |
|---|---|---|---|
| Launch, position and operate (GSO) | 47 CFR 25.164(a) | 5 years after the grant | gso_launch_and_operate@2003-08-27, from |
| 50% constellation deployment (NGSO) | 47 CFR 25.164(b)(1) | 6 years after the grant | ngso_partial_deployment@2017-streamlining, from |
| Full constellation deployment (NGSO) | 47 CFR 25.164(b)(2) | 9 years after the grant | ngso_full_deployment@2017-streamlining, from |
| Surety bond to be posted | 47 CFR 25.165(a) | 30 days after the grant; 1 year 30 days for a licence under 25.122 or 25.123 | surety_bond_ngso@current, from |
| Petitions to deny and other objections | 47 CFR 25.154(a)(2) | 30 days after the public notice | [email protected](a)(2), from |
| A filing date on a weekend or holiday | 47 CFR 1.4(j) | the next business day | [email protected], from |
| Bringing a satellite network into use | ITU Radio Regulations No. 11.44 | 7 years after the date of receipt | [email protected], from |
Worked examples
Computed when this page was built, by the code that computes the dates in the product. The forms above give the same answers.
| Case | Input | Result |
|---|---|---|
| A grant on a leap day | Granted , GSO | 47 CFR 25.164(a) 47 CFR 25.165(a) |
| An NGSO system | Granted , NGSO | 47 CFR 25.164(b)(1) 47 CFR 25.164(b)(2) 47 CFR 25.165(a) |
| A licence under 25.122 | Granted , 25.122 or 25.123 | 47 CFR 25.165(a) |
| A Friday notice, whose thirtieth day is a Sunday | Public notice dated | 47 CFR 25.154(a)(2) 47 CFR 1.4(j) |
| A window whose thirtieth day is Christmas Day | Public notice dated | 47 CFR 25.154(a)(2) 47 CFR 1.4(j) |
| A filing received on a leap day | Received | ITU Radio Regulations No. 11.44 |
The rule's date is the easy half. Orbital Docket reads the Orders themselves: the date each one states, where it differs from the rule, and what the Commission has said since. $99 a month.